Latest entry17 Sep 2026
The SMD boss, first try
Through-hole day: seven pots, the jack, the button, the power header. After yesterday's twenty-four legs, none of it was frightening.

FireFlow · Build log
The instrument already plays. The software is well underway; now the work is turning it into hardware — a compact performance box currently being planned for the bench.


Track 1 of 10
Roadmap · Aug 2026 — May 2027
Three hardware milestones, two board revisions and 23 April as a target corridor rather than a deadline — the dates past the panel freeze get re-anchored once that freeze happens. The graphic below is drawn in two materials, because hardware time comes in two kinds.
Weeks I workWeeks a factory worksMilestoneDecision
A ten-euro test board and a lasered acrylic panel with real knobs on it. Not pretty, but playable — and the panel layout freezes the same day.
Two boards and an aluminium front panel, built and measured. Every fault goes on a list; nothing gets fixed in place, or the next revision never ships.
One correction round, assembled and tested. After this the only work left is firmware, a demo set, and packing a case.
A corridor, not a deadline — re-anchored once the panel layout freezes; the regrouping rounds in Rack come first, before H1. Superbooth opens two weeks later. There is no booth booked and none required; the fair is what happens afterwards.
77 of those 259 days are spent waiting. Boards take three weeks to come back from a factory, and no amount of enthusiasm shortens that — which is why the schedule is built backwards from the last day, and why the cheapest board in the plan is the first one.
Build log
Building in public, in sixteen chapters — from the first commit to the whole engine playing on real hardware. Start with what happened last, or open any chapter below.
Latest entry17 Sep 2026
Through-hole day: seven pots, the jack, the button, the power header. After yesterday's twenty-four legs, none of it was frightening.

78 entries in 16 chapters · open one to read its entries